      25.2.4 any performance test shall be carried out in accordance withthe standards, methods, conditions, procedures and orders which arespecified in appendix 5 (process performance guarantees)hereto, as wellas the technical advice and instructions of the supplier's engineer asspecified in appendix 7-5 (the supplier's engineer's technical servicesand working conditions)hereto.all guarantee figures to be tested are specified in appendix 5(process performance guarantees)hereto. the performance test shall becompleted in _________ days.
      25.2.5 the progress and the result of the performance test shall berecorded in detail by both parties. within three days after the completionof the performance test, the said report of the performance test shall beconfirmed and signed by the representatives of the buyer and the supplier.
    25.3 acceptance
      25.3.1 acceptance shall occur in respect of the contract plant when:
        (a)the performance test has been successfully completed and theprocess performance guarantees specified in appendix 5 (processperformance guarantees)hereto are met; or
        (b)the performance test has not been successfully completed forreasons not attributable to the supplier within _________ months from the
date of the last major shipment as specified in article 25. 2.2 above; or
        (c)the supplier has paid the liquidated damages specified in article28.4 (failure to meet performance guarantees)hereof;
      25.3.2 at any time after any of the events set out in article 25.3.1above has occurred, the supplier may give a notice to the buyer requestingthe issue of an acceptance certificate in respect of the contract plant asat the date of such notice.
      25.3.3 the buyer shall within seven (7)days after receipt of the supplier's notice issue such acceptance certificate.
      25.3.4 if, within seven (7)days after receipt of the supplier' snotice, the buyer fails to issue the acceptance certificate or fails toinform the supplier in writing of the justifiable reasons why the buyerhas not issued the acceptance certificate, the contract plant there of shall be deemed to have been accepted as at the date of the supplier'ssaid notice.