  (7) if the contract shall be terminated as aforesaid, the con -tractor shall be paid by the employer, insofar as such amounts or items shall not have already been covered by payments on account made to the contractor, for all work executed prior to the date of termination at the rate and prices provided in the contract and in addition:
    (a)the amounts payable in respect of any preliminary items, so far as the work or service comprised therein has been carried out or performed, and a proper proportion as certified by the employer of any such items, the work or service comprised in which has been partially carried out or performed.
    (b)the cost of materials or goods reasonably ordered for the works which shall have been delivered to the contractor or of which the contractor is legally liable to accept delivery, such materials or goods becoming the property of the employer upon such payments being made by him.
    (c)a sum being the amount of any expenditure reasonably incurred by the contractor in the expectation or completing the whole of the works insofar as such expenditure shall not have been covered by the payments in this sub - before men - tioned.
    (d)any additional sum payable under the provisions of sub- clauses (1), (2) and (4) of this clause.
  (3) the reasonable cost of removal of constructional plant under sub- (7) of this and, if required by the con - tractor, return thereof to the contractor' s main plant yard in his country of registration or to other destination, at no greater cost.
    (f)the reasonable cost of repatriation of all the contractor's staff and workmen employed on or in connection with the works at the time of such termination.
  provided always that against any payments due from the employer under this sub - clause,the employer shall be entitled to be credited with any outstanding balances due from the contractor for advances in respect of constructional plant and materials and any other sums which at the date of termination were recoverable by the employer from the contractor under the terms of the contract.