  performance under the contract shall, if reasonably possible, continue during the arbitration proceedings and payments due to the contractor by the purchaser shall not be withheld unless they are the subject matter of the arbitration proceedings.
38 notices
  all certificates, notices or written orders to be given by the employer to the contractor under the terms of the contract shall be served by sending by post to or delivering the same to the contractor' s principal place of business, or such other address as the contractor shall nominate for this purpose.
  all notices to be given to the employer under the terms of the contract shall be served by sending by post or delivering the same to the respective addresses nominated for that purpose in these conditions.
39 default of employer
  (1) in the event of the employer:
    (a)failing to pay to the contractor the amount due under any certificate of payment within 90 days after the same shall have become due under the terms of the contract, subject to any de - duction that the employer is entitled to make under the con - tract; or
    (b)interfering with or obstructing or refusing any required approval to the issue of any such certificates; or
    (c)giving formal notice to the contractor that for unforeseen reasons, due to economic dislocation, it is impossible for him to continue to meet his contractual obligations.
  the contractor shall be entitled to terminate his employment under the contract after giving fourteen days' prior written notice to the employer.
  (1) upon the expiry of the fourteen days' notice referred to in sub - (1) of this clause, the contractor shall, notwith- standing the provisions of 30, first paragraph hereof, with all reasonable despath, remove from the site all constructional plant brought by him thereon.
  (2) in the event of such termination the employer shall be under the same obligations to the contractor in regard to pay -ment as if the contract has been terminated under the provisions of 35 (8) hereof ,the employer shall pay to the contractor the amount of any loss or damage to the contractor arising out of or in connection with or by consequence of such termination.