          (a)to investigate the cause for non-fulfillment of the processperformance guarantees, and
          (b)to offer the buyer to change the operating conditions of thecontract plant, and/or
          (c)to make such changes, modifications or additions to theengineering or equipment of the contract plant as considered necessary tomeet the process performance guarantees.
        (3)buyer's permission:the buyer shall allow the supplier necessary time to carry out anyactions deemed necessary by the supplier and the buyer shall make thecontract plant available for that purpose and operate the contract plantin such conditions as requested by the supplier.
        (4)additional test:after the remedial actions stated above are completed the performancetest shall be repeated in the modified part of the contract plant andshall be carried out under the same conditions as provided for the firstperformance test.the performance test shall be repeated as often as the supplier deemsnecessary from the date when the buyer and the supplier shall confirm thatthe contract plant is ready for the performance test pursuant to article25.1.6 of the agreement.
    5. failure in guarantees and liquidated damages
      5.1 failure to attain guaranteed values/levels
        (1)for _________ unit:if the actual production capacity of _________ obtained in theperformance test (or any repeated run thereof)is less than the guaranteedvalue of production capacity of _________ specified in paragraph 3.1 (a)above, but is not less than the minimum level specified in paragraph 5.2(a)below, and/or if the actual average quality of _________ produced duringthe performance test fail to meet the guaranteed levels of quality of_________ specified in paragraph 3.1 (b)above, but meet the minimum levelsspecified in paragraph 5.2 (b)below, and in each/either case the supplierelects to pay liquidated damages to the buyer in lieu of making changes,modifications and/or additions to the _________ unit pursuant toarticle 28.4 of the agreement, then the supplier shall pay liquidateddamages as follows: