    24.2 as soon as the contract plant has, in the opinion of the buyerand the supplier, been completed mechanically and structurally and put ina tight and clean condition, the supplier and the buyer shall confirmcompletion of the erection in writing.
    24.3 within seven (7)days after the confirmation of completion of theerection under article 24.2 above the buyer shall supply the operating andmaintenance personnel specified in appendix 7-1 (scope of works andsupply)hereto for the precommissioning of the contract plant.
      pursuant to appendix 7-1 (scope of works and supply)hereto, the buyershall also provide, within the said seven (7)day period, the rawmaterials, utilities, lubricants, chemicals, catalysts, facilities,services and other matters required for the precommissioning of thecontract plant.
    24.4 as soon as is reasonably practicable after the operating andmaintenance personnel have been supplied by the buyer and the rawmaterials, utilities, lubricants, chemicals, catalysts, facilities, andservices and other matters have been provided by the buyer in accordancewith article 24.3 above, the buyer shall commence the precommissioning ofthe contract plant in preparation for the commissioning.
    24.5 within seven (7)days after all works in respect of theprecommissioning are completed and, in the opinion of the buyer and thesupplier, the contract plant is ready for the commissioning, the buyer andthe supplier shall confirm the readiness for the commissioning in writing.
article 25. commissioning and acceptance
    25.1 commissioning
      25.1.1 the commissioning of the contract plant shall be performed bythe buyer immediately after the confirmation of the readiness for thecommissioning under article 24.5 hereof. the commissioning period shall be_________ months after commencement of the commissioning.
      25.1.2 during the commissioning, the buyer shall supply the operatingand maintenance personnel, raw materials, utilities, lubricants,chemicals, catalysts, maintenance tools, laboratory, testing facilities,facilities, services and other matters required for the operation of thecontract plant as specified in appendix 7-1 (scope of works and supply)hereto.