22.2.11 after the last major shipment is achieved the buyer and thesupplier shall conclude the protocol which confirms the achievement of thelast major shipment. the date of the last major shipment shall be the dateof the bill of lading for the equipment of the last basic lot identifiedin the final delivery schedule.(alternative: cif basis) 22.3 packing and marking 22.3.1 the supplier shall have the equipment properly packed in woodencases and shall take measures to protect the equipment from moisture,rain, rust, corrosion and shock, etc. according to their different shapesand special features so as to withstand numerous handling, loading andunloading as well as long-distance sea and inland transportation to ensurethe safe arrival of the equipment at the contract plant without any damageor corrosion. 22.3.2 the supplier shall mark the following on two (2)sides of eachpackaging case of the equipment with indelible paint in conspicuousenglish printed words: (a)contract no.:_________ (b)shipping mark:_________ (c)destination:_________ (d)consignee:_________ (e)case no. \bale no.:_________ (f)gross\net weight (kg):_________ (g)measurement (length x width x height in cm):_________ 22.3.3 should the equipment weight _________ or more than _________ metrictons, gravity and hoisting position shall be marked in english withinternational trade transportation practice marks and illustrative marksso as to facilitate loading, unloading and handling. in accordance with characteristics and different requirements inloading, unloading and transportation of the equipment, the packaging caseshall be conspicuously marked with "handle with care", "right side up","keep dry" or etc. in english and with appropriate international tradepractice marks and illustrative marks.